The United States now has 684 publicly documented data center projects that are announced, planned, expanding or under construction, according to a Daily Newsfront review updated July 30, 2026. The newest entry is a proposed 1.8-gigawatt artificial-intelligence campus at the former Paducah uranium-enrichment site in Kentucky, where Brookfield Asset Management and NextEra Energy were selected for a federal public-private development.
The short answer: the construction pipeline reaches 49 states, but it is concentrated in a handful of power-rich or fiber-rich markets. Texas leads with 57 projects, followed by Virginia with 44, Georgia with 35, Ohio with 34 and Pennsylvania with 29. Vermont is the only state with no active pipeline project in the database used for this tracker; no active project was listed for Washington, D.C.
This page lists every project in the July 17 snapshot of the open Server Country database whose latest status was announced, planned, under construction or expansion, then adds the Paducah selection and the July 20 Amentum–DC BLOX selection at South Carolina’s Savannah River Site. Operational and canceled projects are excluded. The result is a best-effort public-record inventory, not a permit registry or a promise that every proposal will be built.
How this tracker was built
The base dataset contains 1,048 U.S. data center records and is published under a Creative Commons Attribution 4.0 license by the authors of Data Center Policy across the 50 States. It reports 408 planned projects, 199 under construction, 64 expansions, 11 announced projects, 270 operational facilities and 96 canceled projects as of its July 17 snapshot.
For this page, “pipeline” means a project with a current status of announced, planned, under construction or expanding. It does not mean construction equipment is already on site. “Planned” can cover rezoning, permitting, land assembly, utility study or another preconstruction stage. “Announced” is used when a project has been publicly disclosed but has not yet advanced to a more specific stage.
- Included: new campuses, individual buildings tracked as separate projects, phased developments, major expansions, research and government computing facilities, colocation sites, cloud campuses and AI-focused builds.
- Excluded: projects labeled operational or canceled in the source snapshot, power plants without a named data center project, and speculative sites with no public project record.
- Known limitations: companies often conceal tenants, capacity, water demand, incentives and construction schedules; local filings can lag; projects may be renamed, split into phases or quietly delayed.
The two newest federal-site projects
Paducah, Kentucky: The Department of Energy selected Brookfield to develop and operate a data center at the government-owned Paducah Gaseous Diffusion Plant. NextEra Energy is expected to build and own 2 gigawatts of natural-gas generation and 2.6 gigawatts of battery storage to support a 1.8-gigawatt AI campus. The Associated Press reported that the broader complex carries a $100 billion investment figure and is expected to be completed in 2031, subject to a power-service agreement and regulatory approval.
Savannah River Site, South Carolina: On July 20, the National Nuclear Security Administration selected Amentum to negotiate a phased lease for a 1-gigawatt AI data center paired with roughly 2 gigawatts of on-site generation, initially using natural gas and later nuclear power. DC BLOX is Amentum’s data center partner. The agency stressed that selection for negotiations is not a final lease award and that permitting, safety and security reviews remain.
Piketon, Ohio: The base database already includes the SoftBank PORTS Technology Campus announced March 20. The Department of Energy described a 10-gigawatt data center development supported by 10 gigawatts of new generation, including 9.2 gigawatts of natural gas. Construction was expected to begin in 2026. At that size, it is the single largest power-capacity entry in this tracker.

The national pipeline at a glance
The 684-project total consists of 408 planned, 199 under construction, 64 expanding and 13 announced projects. Because companies do not consistently disclose megawatts or investment and because some campus-level and phase-level figures can overlap, this page does not add every disclosed dollar or megawatt into a national total.
The five largest state pipelines are Texas (57), Virginia (44), Georgia (35), Ohio (34) and Pennsylvania (29). The complete directory below covers all 49 states with an active entry; Vermont and Washington, D.C., have none in this snapshot.

Every announced, planned, expanding and under-construction project
Projects are grouped alphabetically by state. Each entry gives the public project name, reported city or county and a status code: A announced, P planned, UC under construction and E expanding. Detailed sponsor, capacity, investment, timing and research notes are available in the linked open database.
Alabama — 17 projects
- Beacon Calvert Infrastructure Hub — Calvert [P]
- Construction Partners Dothan Corporate Headquarters and Data Processing Center — Dothan [P]
- Core Scientific AUBix Auburn Data Center — Auburn [E]
- DC BLOX Birmingham Expansion — Birmingham [E]
- DC BLOX Huntsville Expansion — Huntsville [E]
- DC BLOX Montgomery Data Center — Montgomery [UC]
- Digi Power X Columbiana AI Data Center — Columbiana [UC]
- Edged Prichard Data Center — Prichard [P]
- Fairfield Colocation Data Center — Fairfield [A]
- Google Bridgeport Data Center — Bridgeport [E]
- Meta Montgomery Data Center — Montgomery [UC]
- Nebius Birmingham AI Factory — Birmingham [UC]
- Project Marvel - Bessemer Hyperscale Data Center — Bessemer [P]
- Project Red Clay — Unknown [P]
- University of Alabama High Performance Computing and Data Center — Tuscaloosa [UC]
- US Space Command Redstone Arsenal Secure Data Center — Redstone Arsenal [P]
- Western Hospitality Childersburg Data Center — Childersburg [P]
Alaska — 6 projects
- Far North Digital Prudhoe Bay Data Center — Prudhoe Bay [P]
- Greensparc Cordova Edge Data Center — Cordova [E]
- Greensparc Petersburg Waterfront Edge Data Center — Petersburg [A]
- Greensparc Wrangell Edge Data Center — Wrangell [P]
- Hilcorp Endicott Bitcoin Mining Pilot — Prudhoe Bay [P]
- STAK Energy Campus — Deadhorse area [P]
Arizona — 25 projects
- 5C Data Centers Phoenix Region (PHX01) — Phoenix [UC]
- Aligned Data Centers Phoenix Campus — Phoenix [E]
- Amazon AWS Phoenix Data Centers — Phoenix and Mesa [UC]
- Amazon AWS Project Blue (Tucson) — Tucson [UC]
- Compass Datacenters Goodyear Campus — Goodyear [UC]
- Google Mesa Data Center (Redhawk) — Mesa [E]
- Grandilla-Foot Creek Tonopah Data Center Campus — Tonopah [P]
- Hassayampa Ranch Data Center — Tonopah [P]
- Huntley Page Data Center — Page [P]
- Luckett Road North and South Data Centers — Marana [P]
- Menlo Digital Phoenix Campus — Phoenix [P]
- Microsoft West US 3 Azure Region — El Mirage and Goodyear [E]
- Novva Data Centers Mesa Campus — Mesa [P]
- NTT Global Data Centers Mesa Campus (Elliot Road) — Mesa [E]
- NTT Global Data Centers Mesa Campus (Pecos & Crismon) — Mesa [P]
- Prime Data Centers Phoenix Campus — Avondale [UC]
- Project Baccara — Glendale area / near Surprise [P]
- QTS Phoenix 3 Campus (Glendale) — Glendale [P]
- RadiusDC Phoenix I Campus — Phoenix [E]
- Ranch House Road Data Center — Marana [P]
- Southwest Crossing Data Center — Casa Grande [P]
- Stream Data Centers Phoenix Campus — Goodyear [E]
- Tract Buckeye Data Center Park — Buckeye [P]
- Vantage Data Centers Phoenix Campus — Goodyear [UC]
- Vermaland La Osa Data Center Park — Eloy area / Red Rock [P]
Arkansas — 6 projects
- Apollo Project - Helena Harbor Data Center — Helena [P]
- AVAIO Digital Leo — Little Rock [UC]
- Clarksville Data Center — Clarksville [UC]
- Conway Data Center (Forgelight Ventures) — Conway [P]
- Google West Memphis Data Center (Project Pyramid) — West Memphis [UC]
- Little Rock Port Data Center (Willowbend Capital) — Little Rock [P]
California — 16 projects
- Amazon AWS Gilroy Data Center — Gilroy [UC]
- Arcadis/Terra Ventures San Jose Sustainable Data Center — San Jose [P]
- AVAIO Pittsburg Perseus Data Center — Pittsburg [P]
- CyrusOne Naval Air Station Lemoore — Lemoore [P]
- DataBank / Goodman LAX2 Vernon Data Center — Vernon [UC]
- ECL Santa Clara CSC-1 — Santa Clara [P]
- EdgeCore Silicon Valley Campus — Santa Clara [UC]
- Goodman Energy Park Data Center — Vernon [P]
- Imperial Valley Data Center Campus — Imperial [P]
- Microsoft San Jose Data Center — San Jose [UC]
- NorthTown Data Center — San Jose [P]
- Prime Data Centers Sacramento Expansion (Building Two) — Sacramento [UC]
- RB Inyokern Data Center — Inyokern [P]
- STACK Infrastructure Hayward (SVY03A) — Hayward [P]
- STACK Infrastructure San Jose Expansion — San Jose [UC]
- T5 Silicon Valley (Newark) — Newark [E]
Colorado — 9 projects
- Cielo Hudson Data Center — Hudson [P]
- CoreSite DE3 Denver Data Center — Denver [UC]
- Flexential Parker Data Center — Parker [UC]
- Fontus Data Centre Project — Unknown [P]
- Global AI Windsor Data Center — Windsor [P]
- NOVVA Colorado Springs Data Center Campus — Colorado Springs [E]
- QTS Aurora-Denver Data Center — Aurora [UC]
- Raeden Project Taurus — Colorado Springs [P]
- Vantage CO21 Aurora Campus — Aurora [P]
Connecticut — 10 projects
- Aphorio Carter Trumbull Data Center — Trumbull [E]
- Atlas Capital Group Bloomfield Data Center — Bloomfield [P]
- Cigna Windsor Data Center — Windsor [E]
- Fairfield County Quantum Computing Center — Stamford [A]
- NE Edge Killingly Data Center — Killingly [P]
- O&G Industries Beacon Falls Data Center — Beacon Falls [P]
- ReNew Amston 1 — Colchester [P]
- ReNew Amston 2 — Colchester [P]
- ReNew Riverside Bristol Technology Center — Bristol [P]
- Wallingford Data Center Development — Wallingford [P]
Delaware — 3 projects
- Project Washington — Delaware City [P]
- St. Georges Business Park Data Center — St. Georges [P]
- White Clay Center Industrial Park Data Center — Newark [P]
Florida — 14 projects
- American Tower Pinellas Park Edge Data Center — Pinellas Park [P]
- Atlas Compute AI Data Center Campus — Fort Pierce [P]
- Cielo Haines City Data Center — Haines City [P]
- CoreSite OR1 Orlando Expansion — Orlando [E]
- DC BLOX Palm Coast Cable Landing Station & Data Center Campus — Palm Coast [UC]
- DCIP DeSoto County AI Data Center — Arcadia [P]
- Fort Meade Data Center Campus — Fort Meade [P]
- HostDime Orlando Data Center — Maitland [UC]
- Iron Mountain Miami Data Center (MIA-1) — Miami [UC]
- Metrobloks Miami Data Center — Miami [P]
- NextNRG Nassau County Data Center & Microgrid Campus — Nassau County (near Jacksonville) [P]
- Osceola County Hyperscale Data Center Campus — Yeehaw Junction [A]
- Project Swan — Lakeland [P]
- RadiusDC Miami I Expansion — Sweetwater [E]
Georgia — 35 projects
- 75 South Data Center Campus — Unknown [P]
- Amazon Web Services - Butts County Campus — Jackson [P]
- Amazon Web Services - Douglas County Campus — Douglasville [P]
- Bridgeport (Revised) — Unknown [P]
- CleanSpark - Sandersville Data Center Campus — Sandersville [P]
- DC BLOX - Atlanta East (Rockdale County) — Conyers [UC]
- DC BLOX - Atlanta West (Douglas County) — Lithia Springs [UC]
- Digital Realty - ATL15/ATL16 (Forest Park) — Forest Park [P]
- Duos Edge AI - Columbus Campus Nistar Deployment — Columbus [E]
- Edged - ATL01-3 — Atlanta [UC]
- Flexential - Atlanta Norcross 2 — Peachtree Corners [P]
- Google - LaGrange Campus — LaGrange [UC]
- Google - Monroe County Campus — Forsyth [P]
- Hampton Technology Park — Hampton [P]
- Microsoft - East Point Campus — East Point [UC]
- Microsoft - Palmetto Campus — Palmetto [UC]
- Microsoft - Project Firecracker (Rome/Floyd County) — Rome [P]
- Microsoft - Project Rita (Tyrone) — Tyrone [P]
- Microsoft - Union City Campus — Union City [UC]
- Newton County Technology Park (Social Circle Technology Park) — Social Circle [P]
- Prime Storage - Powers Ferry Marietta Data Center Conversion — Marietta [P]
- Project Arrowhead — Ocilla area [P]
- Project Azelea — Thomson [P]
- Project Bunkhouse — Stilesboro [P]
- Project Indo — Cartersville [P]
- Project Ruby — Columbus [P]
- Project Sail — Newnan [P]
- Project Springbank — Adairsville [P]
- Project Squash — Harlem [P]
- QTS - Blakely — Blakely [P]
- QTS - Project Excalibur (Fayetteville) — Fayetteville [UC]
- T5 Data Centers - Georgia Campus — Undisclosed [A]
- The Crossings — Union City [P]
- Wallace Jackson Data Center Campus — Unknown [P]
- White Oak Technology Park — Appling [P]

Hawaii — 4 projects
- AlohaNAP Expansion — Kapolei [UC]
- Globalstar / DXN Maui Modular Data Center Deployment — Unknown [P]
- Servpac MTP Data Center — Mililani [UC]
- UH Cancer Center PAC-AID Medical AI Core Data Center — Honolulu [UC]
Idaho — 6 projects
- Aalo Project Ascension On-Site Data Center — Unknown [UC]
- Deep Atomic INL Data Center — Idaho Falls [P]
- Diode Ventures Gemstone Technology Park — Kuna [P]
- Meta Kuna Data Center — Kuna [UC]
- T5 Data Centers - Nampa — Nampa [UC]
- ValorC3 Data Centers - Boise Facility 2 — Boise [UC]
Illinois — 25 projects
- Aligned Data Centers - Elk Grove Village Campus — Elk Grove Village [P]
- CenterSquare ORD2 - 2425 Busse Road — Elk Grove Village [P]
- CenterSquare ORD4 - 4513 Western Avenue — Lisle [P]
- CloudHQ ORD Campus - Mount Prospect — Mount Prospect [UC]
- Compass Datacenters - Hoffman Estates (Former Sears HQ) — Hoffman Estates [UC]
- CyrusOne - Sangamon County Waverly Data Center — Waverly [P]
- CyrusOne - Yorkville Campus — Yorkville [P]
- CyrusOne Aurora Campus — Aurora [UC]
- EdgeConneX - Elk Grove Village 2025 Data Center — Elk Grove Village [P]
- Google Cloud - CME Group Aurora Private Cloud — Aurora [UC]
- Hut 8 - Logan Prairie Data Center — Latham [P]
- HydraVault - Chicago AI Data Center — Chicago [UC]
- Joliet Technology Center — Joliet [P]
- Metro Edge - Illinois Medical District — Chicago [P]
- Microsoft Cherry Valley Campus — Cherry Valley [P]
- Microsoft Plano Campus — Plano [P]
- Oracle America - Elk Grove Village Data Center — Elk Grove Village [P]
- Pioneer Development - Yorkville Project Cardinal — Yorkville [P]
- Prologis - Yorkville Project Steel — Yorkville [P]
- Stream Data Centers - Chicago III (ORDC) — Elk Grove Village [UC]
- T5 @ Chicago IV - Grayslake Campus — Grayslake [P]
- T5 Chicago III - Northlake — Northlake [UC]
- T5 Chicago V - Elk Grove Village — Elk Grove Village [P]
- Tract - Morris Technology Park — Morris [P]
- Whiterose Partners - South Elgin Kenyon Road Data Center — South Elgin [P]
Indiana — 18 projects
- Amazon Web Services (AWS) Hobart Tech Park — Hobart [P]
- Amazon Web Services (AWS) New Carlisle Campus — New Carlisle [UC]
- Amazon Web Services (AWS) Wheatfield/Jasper County Campus — Wheatfield [P]
- DC BLOX Thunderbird Commerce Center Data Center — Indianapolis [P]
- Google Michigan City Data Center (Project Maize) — Michigan City [UC]
- JPG Data Center — Madison [P]
- La Porte One / Project Cardinal Thomas Rose Industrial Park Data Center — La Porte [P]
- Meta Jeffersonville Data Center — Jeffersonville [UC]
- Meta Lebanon LEAP District Campus — Lebanon [UC]
- Metrobloks Martindale-Brightwood Data Center — Indianapolis [P]
- Microsoft La Porte Data Center — La Porte [UC]
- Microsoft Mishawaka/Granger Data Center — Granger [UC]
- Morgan County Data Center (Project Louie) — Monrovia [P]
- Next Frontier / Fluidstack New Lebanon Data Center — New Lebanon [P]
- Prologis Shelbyville Data Center (Project Hackman) — Shelbyville [P]
- Sabey Decatur Township Data Center — Indianapolis [P]
- Sentinel Data Centers Project Shirley Eagle Creek Township Campus — Hebron [P]
- Surge Development Knightstown Data Center — Knightstown [P]
Iowa — 17 projects
- Cascade Industrial Park Data Center — Cascade [P]
- COPT Defense Properties - Van Meter Campus — Van Meter [P]
- Edged - Ankeny Data Center — Ankeny [UC]
- Edged - Council Bluffs Campus (EDC Omaha) — Council Bluffs [UC]
- Google - Cedar Rapids Campus — Cedar Rapids [UC]
- Google - Council Bluffs Campus (Expansions) — Council Bluffs [E]
- Google - Palo Data Center Project (Near Duane Arnold) — Palo [P]
- Karis Critical - Dubuque County Data Center — Unknown [P]
- Lightedge - Ames Aviation Way Edge Colocation Facility — Ames [P]
- Meta - Davenport Data Center Campus — Davenport [P]
- Microsoft - Van Meter Vision Park Campus — Van Meter [P]
- Microsoft - West Des Moines Campus (6th Data Center) — West Des Moines [P]
- Oppidan Connect - Cedar Rapids 33rd Avenue Data Center — Cedar Rapids [UC]
- QTS - Cedar Rapids Campus — Cedar Rapids [UC]
- QTS - Clinton Data Center Campus — Clinton [P]
- Tract - Altoona Technology Park — Altoona [P]
- Tract - Norwalk Project West Data Center Campus — Norwalk [P]
Kansas — 12 projects
- Alcove Osawatomie Northland Data Center — Osawatomie [P]
- Compass Datacenters Shawnee County Proposal — Topeka area [P]
- De Soto Data Center Campus (Project Pilot) — De Soto [UC]
- Digital Realty De Soto Data Center Development — De Soto [P]
- Flint Hills Digital Campus — Emporia [P]
- Google Barber County Data Center (Project Helium) — Sharon [P]
- Heartland Data Center Project — Edgerton [P]
- Lightfield Energy Proximity Park Technology Campus — Ottawa [P]
- Prairie Horizon Data Campus — near St. Marys [P]
- Project Bluestem Leavenworth County Data Center — Tonganoxie [A]
- Red Wolf DCD Properties Data Center Campus — Kansas City [P]
- Vine Energy Iola Data Center — Iola [UC]
Kentucky — 9 projects
- Brookfield–NextEra Paducah AI Data Center Campus — Paducah area [A]
- DartPoints Lexington Data Center — Lexington [E]
- Franklin-Simpson Data Storage and Service Center — Franklin [P]
- Justified Data Campus — Hawesville [P]
- Mason County Technology Campus — Maysville area [P]
- MD Squared Power Pikeville Data Center — Pikeville [P]
- Mercer County Data Center (Handy Road) — Burgin area [P]
- PowerHouse Data Centers Louisville Campus — Louisville [UC]
- TeraWulf Muskie Data Campus — Wurtland area [P]
Louisiana — 5 projects
- Amazon/STACK Northwest Louisiana Data Center Campuses — Blanchard/Benton [UC]
- Applied Digital Delta Forge 1 AI Factory Campus — Boyce [UC]
- Hut 8 West Feliciana AI Data Center — St. Francisville [UC]
- Hyperscale Data Offshore Bitcoin Mining Pilot — Offshore [A]
- Meta Richland Parish AI Data Center (Hyperion Campus) — Rayville/Delhi [UC]
Maine — 5 projects
- DeepGreen Western Passage Subsea AI Data Center — Eastport [P]
- Green 4 Maine Data Center Campus — Limestone [P]
- Sanford Woods Industrial and Technical Campus — Sanford [P]
- Scarborough Technology Park Data Center — Scarborough [P]
- Wiscasset Data Center (Proposed) — Wiscasset [P]
Maryland — 12 projects
- Aligned Data Centers - Critical Digital Infrastructure Facility — Adamstown [UC]
- AWS Calvert Cliffs Data Center Campus — Lusby area [P]
- Brightseat Tech Park — Landover [P]
- Dickerson Power Plant Data Center Proposals — Dickerson [P]
- Johns Hopkins University - Data Science and Computing Infrastructure Data Center — Baltimore [P]
- Natelli Holdings - Appeal Digital Park — Lusby [P]
- Quantum Frederick Campus — Adamstown [UC]
- Rowan Digital Infrastructure - Bauxite II — Adamstown [UC]
- Rowan Digital Infrastructure - Bauxite III — Adamstown [P]
- Security Land Baltimore Data Center — Woodlawn [P]
- TeraWulf - Chesapeake Data & Energy — Newburg [P]
- TPC Data Centers - Konterra 1 — Laurel [P]
Massachusetts — 3 projects
- Amazon AWS Worcester County Properties — Westborough, Grafton [P]
- Markley Lowell Data Center — Lowell [E]
- Westfield Data Center Campus (Servistar Realties) — Westfield [P]
Michigan — 19 projects
- Alterra Marshall Technology Center — Marshall [P]
- Form8tion Augusta Township Data Center — Augusta Township [P]
- Google Van Buren Township Data Center Campus (Project Cannoli) — Van Buren Township [P]
- Hyperscale Data Michigan Campus — Dowagiac [E]
- Mason Data Center at 3388 W Columbia Road — Mason [P]
- Metrobloks Southfield Data Center — Southfield [P]
- Microsoft Dorr Township Data Center — Dorr Township [P]
- Microsoft Gaines Township Site — Gaines Township [P]
- Microsoft Lowell Charter Township Data Center — Lowell Charter Township [P]
- Oakland University Campus Computing Facility — Rochester Hills [P]
- OpenAI Stargate - Saline Township Campus — Saline Township [UC]
- Project Cherry Blossom Frenchtown Data Center — Frenchtown Township [P]
- Project Flex Data Center — Lyon Township [P]
- Project Ironwood Dundee Data Center — Dundee Township [P]
- Raeden Gibraltar McLouth Steel Data Center — Gibraltar [P]
- Switch SUPERNAP Grand Rapids Campus — Grand Rapids [E]
- Tondu Stronach Township Data Center Concept — Stronach Township [P]
- University of Michigan & Los Alamos National Laboratory Data Center — Ypsilanti Township [P]
- US Signal Detroit Metro Expansion — Belleville [E]
Minnesota — 17 projects
- Archer Datacenters Faribault Campus — Faribault [P]
- BlockchAIn Crow Wing County Data Center — Unknown [P]
- Centra MSP1 Data Center — Eagan [UC]
- Cloud Capital Minneapolis Data Center Expansion — Minneapolis [E]
- CloudHQ MSP Campus (Chaska) — Chaska [P]
- Elk River Industrial Boulevard Data Center — Elk River [P]
- Hampton Data Center — Hampton [P]
- Hermantown Data Center — Hermantown [P]
- Meta Rosemount Data Center — Rosemount [UC]
- Microsoft Becker Data Center — Becker [P]
- Monticello Tech/Monticello Industrial Park — Monticello [P]
- Pine Island Data Center (Project Skyway) — Pine Island [P]
- Scannell Technology Park — Monticello [P]
- Shakopee Capital Dean Lakes Data Center — Shakopee [P]
- T5/QLevr Inver Grove Heights Data Center — Inver Grove Heights [P]
- Tract Cannon Falls Technology Park — Cannon Falls [P]
- Tract Farmington Technology Park — Farmington [UC]
Mississippi — 10 projects
- AVAIO Digital Taurus Data Center Hub — Brandon [UC]
- AWS Clinton Data Center Project — Clinton [P]
- AWS Madison County Data Center Campus — Canton and Ridgeland [E]
- AWS Madison County Expansion Phase — Canton and Ridgeland [E]
- AWS Vicksburg Data Center Campus — Vicksburg [P]
- Clarksdale Data Center Project — Clarksdale [P]
- Compass Datacenters Meridian Campus — Meridian [UC]
- Prado AI Industrial Campus — Unknown [P]
- Saxum Forest Avenue Jackson Data Center Site — Jackson [P]
- xAI Southaven MACROHARDRR Data Center — Southaven [UC]
Missouri — 19 projects
- Amazon Project Green New Florence Data Center Campus — New Florence [P]
- Armory Innovation Data Center (Famous-Barr Warehouse) — St. Louis [P]
- Beltline Energy Meramec Valley Technology Park — Pacific area [P]
- CRG Festus Data Center — Festus [P]
- Crusoe Warrenton Campus — Warrenton [P]
- Gateway Digital Campus (Diamond Farms) — Villa Ridge [P]
- Google Kansas City Data Center — Kansas City [UC]
- Google New Florence Data Center Campus — New Florence area [P]
- Marshfield Area Data Center (Rifle Range Road) — Marshfield area [UC]
- Metrobloks Liberty Data Center Campus — Liberty [P]
- Metrobloks MCI-A Kansas City — Kansas City [P]
- Nebius Independence Data Center Campus — Independence [UC]
- Patmos AI Campus (Kansas City Star Building) — Kansas City [E]
- Project Blitz (Lambda Northland AI Factory) — Kansas City [UC]
- Project Kestrel — Kansas City [P]
- Project Mica (Google AI Campus) — Kansas City [UC]
- TierPoint St. Louis Data Center — St. Louis [UC]
- White Cloud Acres AI Data Center — Maryville area [P]
- Wildwood Ranch / Joplin Data Center — Joplin [P]
Montana — 2 projects
- Bitzero - Polson Facility — Polson [P]
- Quantica Infrastructure - Big Sky Digital Infrastructure Campus — Broadview [P]
Nebraska — 5 projects
- AAIM Nebraska 2 Data Center — Unknown [UC]
- Fortitude Mining Grand Island Data Center — Grand Island [UC]
- Google Lincoln Data Center (Agate Project) — Lincoln [UC]
- Google-Tenaska Southeast Nebraska Data Center — Unknown [P]
- Sequitor Edge Kearney Data Center — Kearney [P]
Nevada — 18 projects
- Blackjack Data Center — Pahrump [P]
- Centra RNO2 Reno Data Center — Reno [UC]
- Colovore RNO01 Reno Data Center — Reno [UC]
- EdgeCore Reno Campus — Reno/Sparks [UC]
- Fleet Reno / Storey County Hyperscale Campus — Reno-Sparks area [UC]
- Microsoft Silver Springs Data Center — Silver Springs [P]
- Monarch Data Center — Yerington [P]
- Oppidan North Valleys Data Center — Reno [P]
- Osprey Data Center — Pahrump [P]
- PowerHouse Reno Data Center — Reno/Sparks [UC]
- Switch Citadel Campus (Tahoe Reno) — Reno/Sparks [E]
- Switch CORE Campus Las Vegas — Las Vegas [E]
- TerraScale Energos Reno — Fernley [P]
- Townsite Solar 2 Boulder City Data Center — Boulder City [P]
- Tract Peru Shelf Technology Park — Reno/Sparks [UC]
- Tract Silver Springs Data Center Park — Silver Springs [P]
- Tract South Valley Technology Park — Reno/Sparks [UC]
- Vantage Data Centers NV1 Campus — Reno/Sparks [UC]
New Hampshire — 1 project
- FirstLight Bedford Data Center (formerly ColoSpace) — Bedford [E]
New Jersey — 9 projects
- Chirisa PNJ-01 / PNJ-02 Piscataway Campus — Piscataway [P]
- Comcast Clinton Data Center — Clinton [P]
- CoreWeave NEST Campus — Kenilworth [UC]
- Equinix New York Metro Expansion — Secaucus [E]
- Nebius New Jersey AI Data Center — Vineland [UC]
- NJFX Project Cool Water — Wall Township [E]
- Princeton Nurseries Data Center — South Brunswick [UC]
- Prism ON3 Data Center — Nutley [P]
- QTS East Windsor — East Windsor [E]
New Mexico — 5 projects
- Atterix Raton Advanced Digital Hub — Raton [P]
- Meta Los Lunas Data Center Campus — Los Lunas [E]
- New Era Lea Data Center — Unknown [P]
- Project Jupiter (Stargate Santa Teresa Campus) — Santa Teresa [UC]
- Zenith Volts Roswell Data Center — Roswell [P]
New York — 18 projects
- Blockfusion Niagara Falls Campus Expansion — Niagara Falls [E]
- Broome County Tech Park Data Center — Unknown [P]
- ColoCrossing Buffalo Expansion — Buffalo [E]
- Greenidge 200 MW Data Center Project — Unknown [P]
- Indian Point Data Center Campus Redevelopment — Buchanan [P]
- iPark 84 Data Center Interconnection — East Fishkill [P]
- JPMC Datacenter II Orangeburg Expansion — Orangeburg [UC]
- Kenwood Tech Center — Albany [P]
- Niagara Digital Campus — Niagara Falls [P]
- North Country Collocation Services Massena Expansion — Massena [E]
- Pontoon Bridge Road Data Center — Unknown [P]
- Ranalli Lysander Data Center — Lysander [P]
- Remington Factory Redevelopment AI Data Center — Ilion [P]
- Riverview Innovation and Technology Campus — Tonawanda [P]
- Stream Data Centers STAMP Campus — Alabama [P]
- TeraWulf Lake Hawkeye (Cayuga) — Lansing [P]
- TeraWulf Lake Mariner (Core42 Lease) — Somerset [E]
- Treetop Companies East Fishkill Data Center — East Fishkill [P]
North Carolina — 14 projects
- Amazon Web Services (AWS) Richmond County Campus — Richmond County [UC]
- American Tower East Charlotte Hood Road Data Center — Charlotte [P]
- Compass Datacenters Statesville Campus — Statesville [A]
- Digital Realty CLT10 East Trade Expansion — Charlotte [E]
- Digital Realty Moores Chapel Road Charlotte Campus — Charlotte [P]
- Drox Rural Hall Data Center (Project Iron Spur) — Rural Hall [P]
- Eco TIP West Moncure Data Center — Moncure [P]
- Google Lenoir Data Center — Lenoir [E]
- Microsoft Catawba County Campus — Multiple locations [UC]
- Microsoft Person County Mega Park — Roxboro [P]
- Natelli Henderson Data Center — Henderson [P]
- PowerHouse Data Centers Charlotte Campus — Charlotte [UC]
- Project Delta Stokes County Data Center — Walnut Cove [P]
- WhiteFiber NC-1 Madison Data Center — Madison [UC]
North Dakota — 11 projects
- Applied Digital Oliver County AI Factory — Center area [P]
- Applied Digital Polaris Forge 1 — Ellendale [E]
- Applied Digital Polaris Forge 2 — Harwood [UC]
- Aurum Bismarck Campus — Bismarck [P]
- Bitzero Nekoma Pyramid Data Center — Nekoma [P]
- Enerfore Digital Pleasant Valley Data Center — Tioga area [P]
- Nakota AI Data Campus — Unknown [P]
- Project Fighting Pike — Williston [P]
- Project Trinity — Tioga area [P]
- Rainbow Energy Coal Creek Data Center Park — Underwood [P]
- River Run Energy Center Data Center Campus — Stanton area [P]
Ohio — 34 projects
- 5C Data Centers CMH01 — Springfield (Columbus area) [UC]
- Aligned CMH-02 Conesville Data Center Campus — Conesville [UC]
- Aligned NEO-01 Campus — Perkins Township (Sandusky area) [UC]
- AWS Marysville Innovation Park Data Center Campus — Marysville [P]
- AWS Project Galaxy Sidney Data Center — Sidney [P]
- AWS Wilmington Data Center Campus — Wilmington [P]
- Bitdeer Clarington Hannibal Industrial Park Data Center — Clarington / Hannibal [P]
- Bitdeer Massillon Data Center Campus — Massillon [UC]
- Bitdeer Niles Data Center Campus — Niles [P]
- Bitdeer Shalersville Data Center Campus — Shalersville Township [P]
- Bristolville AI Data Center — Bristolville [P]
- Cologix Johnstown Campus — Johnstown [UC]
- EdgeConneX Ashville Data Center Campus — Ashville [P]
- EdgeConneX New Albany Data Center Campus — New Albany [UC]
- Google Central Ohio Campuses — New Albany, Columbus, Lancaster [E]
- Google Project BOSC Lima Data Center — Lima / American Township [UC]
- Google Project Dazzler Scioto County Data Center — Franklin Furnace [P]
- Grove City Data Center Campus — Grove City [P]
- Meta Bowling Green Data Center — Bowling Green [UC]
- Meta Marysville South Data Center — Marysville [P]
- Meta Piqua Data Center — Piqua [P]
- Meta Prometheus (New Albany Campus) — New Albany [UC]
- Microsoft Licking County Campuses — New Albany, Heath, Hebron [UC]
- OpenAI Stargate Lordstown Campus — Lordstown [UC]
- Pacifico Muhlenberg Township Data Center — Muhlenberg Township [P]
- Panattoni Perry Township Data Center — Perry Township [P]
- Prologis Project Mila Trenton Data Center Campus — Trenton [UC]
- Province Group Perry Village Data Center Campus — Perry Village [P]
- QTS New Albany Campus — New Albany [UC]
- SoftBank PORTS Technology Campus — Piketon [UC]
- Thor Urbana Data Center Campus — Urbana [P]
- Van Wert Mega Site Data Center — Van Wert [P]
- Vantage OH1 Campus — New Albany [UC]
- Vantage OH2 Millersport Data Center Campus — Millersport [P]
Oklahoma — 17 projects
- Beltline Energy Luther Data Center — Luther [P]
- Beltline Energy Yukon Data Center — Yukon [P]
- BLE Landholdings Piedmont Data Center — Piedmont [P]
- CoreWeave/Core Scientific Muskogee Data Center — Muskogee [E]
- DAMAC/EDGNEX Oklahoma Data Centers — Unknown [A]
- Google Mayes County (Pryor) Data Center Expansion — Pryor [E]
- Google Muskogee County Data Center Campuses — Summit; Council Hill [P]
- Google Project Spring Sand Springs Data Center — Sand Springs [P]
- Google Stillwater Data Center Campus — Stillwater [UC]
- IREN Oklahoma Data Center Campus — Unknown [P]
- Oklahoma AI Ventures Data Center Campuses — Unknown [P]
- Polaris Technologies Bitcoin Mining Data Center — Muskogee [UC]
- Potentia Oklahoma Campus 02 — Inola [P]
- Project Anthem (Tulsa East) — Tulsa [UC]
- Project Clydesdale (Tulsa County/Owasso) — Owasso [UC]
- Project Mustang Claremore Data Center — Claremore [P]
- Project Open Sky — Piedmont [P]
Oregon — 14 projects
- Aligned Data Centers Hillsboro Campus (PDX-01/PDX-02) — Hillsboro [UC]
- Amazon AWS Arlington Expansion — Arlington [P]
- Amazon AWS Hermiston Data Centers — Hermiston [UC]
- Amazon AWS US West (Oregon) Region - Boardman — Boardman [E]
- Amazon Boardman Exascale Data Center Site — Boardman [P]
- Apple Prineville Data Center Campus — Prineville [E]
- Crane Data Centers Forest Grove Campus (PDX01) — Forest Grove [UC]
- EdgeConneX Portland Data Center Campus — Hillsboro [E]
- Flexential Hillsboro Data Center Campus — Hillsboro [E]
- Google The Dalles Data Center Campus — The Dalles [E]
- QTS Hillsboro Data Center Campus — Hillsboro [E]
- Sabey Data Centers Umatilla Campus (SDC Umatilla) — Umatilla [UC]
- Stack Infrastructure POR03 Expansion — Hillsboro [E]
- Verrus Oakline at Mill Creek Data Center Campus — Salem [P]
Pennsylvania — 29 projects
- Amazon Web Services AI Innovation Campuses — Salem Township; Falls Township; Kline Township [UC]
- Blackstone-QTS Northeastern Pennsylvania Data Centers — Salem Township [P]
- CoreWeave Lancaster County AI Data Center — Lancaster [P]
- Emaus Avenue Data Center — Allentown [P]
- fifteenfortyseven Chester County Hyperscale Campus — East Whiteland Township [P]
- Gouldsboro Data Center Campus — Gouldsboro (Clifton and Covington Townships) [P]
- HCI DP Land Acquisition South Hanover Quarry Data Center Campus — South Hanover Township [P]
- Homer City Energy Campus — Homer City [UC]
- Keel Panther Creek HPC/AI Data Center Campus — Nesquehoning [P]
- Keel Scrubgrass AI/HPC Data Center Campus — Kennerdell / Scrubgrass Township [E]
- Keel Sharon Data Center Expansion — Sharon [E]
- Lower Mount Bethel Tech Center — Lower Mount Bethel Township [P]
- Microsoft Three Mile Island Energy Supply — Londonderry Township [P]
- MRP Industrial Watts Township Data Center Campus — Watts Township [P]
- Nebius Pennsylvania AI Factory Campus — Unknown [P]
- PA Data Center Partners Granville Township Data Center — Granville Township [P]
- Pennsylvania Digital I (PAX) — Carlisle [UC]
- Popca Newton Township Data Center Campus — Newton Township [P]
- Project Atlas — South Whitehall Township [P]
- Project Gravity — Archbald [P]
- Project Green Mountain — Archbald [P]
- Prologis Lehigh Valley East 16 Data Center Conversion — Allen Township [P]
- Shippingport Power Station and Data Center — Shippingport [P]
- Smithfield Gateway Data Center — Smithfield Township [P]
- Soltier Towanda Crypto Data Mine — Towanda / Wysox Township [P]
- Stonebridge Powder Mills Data Center Campus — North Beaver Township and Mahoning Township [P]
- TECfusions Keystone Connect — Upper Burrell [UC]
- Wildcat Ridge AI Data Center Campus — Archbald [P]
- York 2 Energy Center Data Campus — Peach Bottom Township [P]
Rhode Island — 1 project
- Hanton City Investments Smithfield Data Center — Smithfield [P]
South Carolina — 15 projects
- Amentum–DC BLOX Savannah River Site AI Data Center — Savannah River Site [A]
- Cielo Digital Infrastructure Cherokee County Campus — Gaffney [P]
- DartPoints Columbia Data Center — Columbia [E]
- DartPoints Greenville Data Center — Greenville [UC]
- DC BLOX Camp Hall Hyperscale Campus — Ridgeville [A]
- DC BLOX North Augusta Hyper Edge Facility — North Augusta [UC]
- Eagle Rock Partners Colleton County Data Center Campus — Walterboro area [P]
- Google Berkeley County Data Center Campus — Moncks Corner [E]
- Google Pine Hill Business Campus Data Center — Ridgeville [UC]
- Google Winding Woods Commerce Park Data Center — St. George [UC]
- LightHouse Data Centers Spartanburg 300 Jones Road Campus — Spartanburg [P]
- Meta Sage Mill Industrial Park Data Center — Aiken [UC]
- Oppidan Sage Mill Industrial Park Data Center — Graniteville [UC]
- Project Moc-1 (NorthMark Strategies) — Spartanburg [UC]
- QTS York County Data Center Campus — York County (unincorporated) [UC]
South Dakota — 4 projects
- Gemini Data Center Sioux Falls — Sioux Falls [P]
- Leola Data Center — Leola [P]
- Sequitor Edge Brookings Research Park Data Center — Brookings [P]
- Sequitor Edge Rapid City Data Center — Rapid City [P]
Tennessee — 10 projects
- 5C MEM01 Memphis Data Center — Memphis [P]
- Cielo Clarksville Data Center — Clarksville [P]
- DC BLOX Nashville Campus — Nashville [P]
- Evoque-Archer Nashville Campus — Gallatin [UC]
- Fisk Quantum Leap Innovation & Technology Center — Nashville [P]
- Hixson Data Center — McMinnville [P]
- Jailhouse Studios AI Data Center — Chattanooga [P]
- Lawrenceburg Flatwoods Road Data Center — Lawrenceburg [P]
- RadiusDC Nashville I — Nashville [UC]
- xAI Colossus Supercomputer — Memphis [E]
Texas — 57 projects
- Aligned Data Centers - Mansfield DFW-03 — Mansfield [UC]
- Aligned Project Caprock — Abernathy area [UC]
- Amazon Data Services Creekside Campus — Cedar Creek area [P]
- AWS - Round Rock Data Center — Round Rock [P]
- Black Mountain Fort Worth Data Center — Fort Worth [P]
- Blueprint Projects - Taylor Data Center — Taylor [UC]
- BT Gateway Data Center — Royse City [P]
- CloudBurst Central Texas Flagship Campus — San Marcos / New Braunfels area [UC]
- Core Scientific Pecos AI/HPC Campus Expansion — Pecos [E]
- Crow Holdings / CleanArc Central Dallas Campus — Dallas [P]
- Crusoe Energy Nolan County Data Center — Sweetwater [P]
- CyrusOne / Constellation Freestone Energy Center Data Center Campus — Fairfield area [UC]
- CyrusOne & Calpine - DFW10 Whitney Campus — Whitney [UC]
- CyrusOne DFW7 - Fort Worth — Fort Worth [UC]
- Data City Texas — Near Laredo [P]
- DataBank South Dallas / Red Oak Campus — Red Oak [UC]
- Digital Realty - Garland Campus Expansion — Garland [UC]
- ECP & KKR - Bosque County Campus — Near Whitney [UC]
- EdgeConneX Cedar Creek Campus 2 — Cedar Creek [P]
- Edged Data Centers - Veale Ranch Fort Worth Campus — Fort Worth [P]
- Edged Energy-Austin — Maxwell [UC]
- Galaxy Helios Phase 2 — Afton [UC]
- Galaxy Project Merlin McGregor Data Center — McGregor [P]
- GigaPop Data Center — Red Oak [P]
- Google Meitner Energy Center Data Center — Unknown [UC]
- Google Wilbarger County Data Center — Vernon area [UC]
- Hut 8 Beacon Point AI Data Center Campus — Unknown [UC]
- LandBridge / PowerBridge Alpha Digital Data Center Campus — Waha area [P]
- Meta - Temple Data Center — Temple [UC]
- Meta El Paso Data Center — El Paso [UC]
- Microsoft - Medina County Data Centers — Castroville Area [UC]
- Microsoft - San Antonio Data Center Campus — San Antonio [E]
- Nightpeak Old Ocean Data Center — Sweeny area [P]
- NTT Data - Garland Expansion — Garland [E]
- Pace Glasscock County Texas-First Data Center — Unknown [P]
- Palomino Alpha Guadalupe County Data Center — Unknown [P]
- PowerHouse & Provident - Grand Prairie Campus — Grand Prairie [P]
- PowerHouse Austin / Caldwell Valley Data Center — Uhland area [P]
- Project Aquila — Hillsboro area [P]
- Project Comal — Taylor area [P]
- Prometheus Hyperscale Dallas Campus — Dallas [P]
- Provident Data Centers Hillsboro Campus — Hillsboro [P]
- QTS / Lancium Hall County Clean Campus — Turkey [P]
- Rowan Cinco Data Center — Lytle area [UC]
- Rowan Temple Data Center Campus — Temple [UC]
- Sailfish Comanche Circle Data Center — Tolar area [P]
- Skybox Datacenters - PowerCampus Austin — Hutto [UC]
- Skybox PowerCampus Texas - Wichita Falls — Wichita Falls [P]
- Stargate Project - Abilene Campus (Oracle/Crusoe) — Abilene [UC]
- Stargate Project - Milam County Site — Unknown [UC]
- Stream Data Centers - Graham / Plug Power Site — Graham [P]
- Stream Data Centers - San Antonio III — San Antonio [UC]
- Texas Critical Data Centers (TCDC) - Ector County — Odessa Area [P]
- Tract Applewhite Technology Park — San Antonio [P]
- Tract Caldwell Valley Technology Park — Uhland / Lockhart area [P]
- Tract Medina Technology Park — Castroville area [P]
- Vantage Data Centers - Frontier Campus — Unknown [UC]
Utah — 17 projects
- Antelope Data Center — Cedar City area [P]
- BluSky AI Delta Data Center — Delta [P]
- BluSky AI Milford Campus — Milford area [P]
- BluSky AI Nephi — Nephi [P]
- Cirrus Data Services - View 78 Campus — Midvale [P]
- CyrusOne Dugway Proving Ground — Dugway Proving Ground [P]
- Data Center Power Company - Summit Ridge Data Center — Santaquin [P]
- Delta Gigasite / Fibernet MercuryDelta — Delta [UC]
- Google - Eagle Mountain Land Acquisition — Eagle Mountain [P]
- Joule Capital Partners - Millard County Campus — Delta area [UC]
- Nine Mile Data Center — Myton area [P]
- Novva Data Centers - West Jordan Campus — West Jordan [UC]
- QTS Eagle Mountain Data Center Campus — Eagle Mountain [UC]
- Red Butte Energy and Data Center Campus — Newcastle area [P]
- Tract - Project Tripletail — Eagle Mountain [P]
- Volition Industries - Spanish Fork Data Center — Spanish Fork [P]
- Wonder Valley Utah / Stratos AI Data Center Campus — Golden Spike area [P]
Virginia — 44 projects
- AWS Louisa County Campus 1 — Louisa [P]
- AWS Spotsylvania County Campus — Spotsylvania [UC]
- BlackChamber Virginia Portfolio — Virginia [UC]
- CleanArc Virginia Hyperscale Campus — Unknown [UC]
- CloudHQ LC Campus — Ashburn [UC]
- CloudHQ LC4 — Ashburn [UC]
- Crusoe Project Flash Franklin County — Unknown [P]
- CyrusOne ABX-1 Ashburn (PowerHouse Lease) — Ashburn [UC]
- CyrusOne Future Hyperscale Campus — Loudoun County [P]
- DataBank Culpeper Campus — Culpeper [UC]
- Digital Realty Digital Dulles Campus — Dulles [UC]
- EdgeCore AS01 and AS02 Sterling Data Centers — Sterling [UC]
- EdgeCore Ashburn Facility — Ashburn [UC]
- EdgeCore Culpeper Campus — Culpeper [UC]
- EdgeCore Louisa County Campus — Louisa [P]
- Google Botetourt County Data Center Campus — Daleville [P]
- Google Chesterfield County Campus (Project Peanut) — Chester [UC]
- Google Project Loch Chesterfield Campus — Midlothian [P]
- Google Project Skye Chesterfield Campus — Moseley area [P]
- HighBrook Northern Virginia Development Portfolio — Northern Virginia [P]
- Hopewell Former Ethanol Plant Data Center — Hopewell [P]
- Iron Mountain Manassas Campus — Manassas [P]
- Iron Mountain Richmond Campus — Richmond [UC]
- Meta Henrico Expansion (Project Tropical) — Sandston [P]
- Microsoft Leesburg Campus — Leesburg [UC]
- Microsoft Manassas Jacksonville Road Campus — Manassas [UC]
- Microsoft Mass Timber Data Centers — Northern Virginia [UC]
- Microsoft Mecklenburg County Data Center Expansion — Boydton area [E]
- PowerHouse 95 Campus — Spotsylvania [UC]
- Project Tallmadge Strasburg Data Center — Strasburg [P]
- Province Group Powhatan Technology Park — Powhatan [P]
- QTS Richmond Expansion — Richmond [E]
- Remington Digital Campus — Remington [P]
- Remington Technology Park — Remington [UC]
- Stack Infrastructure Berry Hill Megasite — Berry Hill [P]
- Stack Infrastructure Loudoun County Campus — Ashburn [A]
- Stack Infrastructure Stafford Technology Campus — Stafford [UC]
- T5@Dulles Chantilly Fuel Cell Data Center — Chantilly [P]
- TA Digital Sterling Thayer Road Data Center — Sterling [P]
- Tract Tuckahoe Technology Park — Goochland area [P]
- Vantage VA2 Campus (Ashburn II) — Ashburn [UC]
- Vantage VA3 Campus (Ashburn III) — Ashburn [P]
- Vantage VA4 Campus (Fredericksburg) — Unknown [P]
- Yondr JK Loudoun County Campus Expansion — Unknown [E]
Washington — 10 projects
- Advance Phase LLC Walla Walla Campus (Project Tree) — Wallula [P]
- Atlas Agro Richland Data Center Campus — Richland [P]
- Colossus Starbucks Center Seattle Data Center — Seattle [P]
- Digital Realty 301 Virginia Street Seattle Data Center — Seattle [P]
- Microsoft East Wenatchee Campus — East Wenatchee [UC]
- Microsoft Malaga Campus — Malaga [UC]
- Pacific Northwest National Laboratory On-Premises Next-Gen AI Compute Data Center — Richland [P]
- Pacland 3625 First Avenue South Seattle Data Center — Seattle [P]
- Port of Walla Walla - Project Forest — Walla Walla [P]
- Trammell Crow Lewis & Clark Ranch Data Center — West Richland [P]
West Virginia — 10 projects
- Adams Fork Data Center Energy Campus - Harless Site — Holden [P]
- Adams Fork Data Center Energy Campus - Wharncliffe Site — Wharncliffe [P]
- Alpha Technologies Huntington Data Center — Huntington [P]
- Berkeley/Jefferson County Data Center Campus — Near Kearneysville [P]
- Fundamental Data Tucker County Data Center — Between Thomas and Davis [P]
- Google Putnam County Data Center Campus — Buffalo [P]
- NETL Computational Science and Engineering Center — Morgantown [UC]
- Nscale / Microsoft Monarch Compute Campus AI Infrastructure Phase — Point Pleasant area [UC]
- Penzance Bedington Data Center Campus — Falling Waters District [P]
- Ryan Stuart Summit Point Data Center Project — Summit Point [P]
Wisconsin — 10 projects
- Balloonist Red Cedar / Menomonie Data Center — Menomonie / Red Cedar [P]
- Cloverleaf Wrightstown Data Center Prospect — Wrightstown area [P]
- Meta Platforms Data Center - Beaver Dam — Beaver Dam [UC]
- Meta Project Cornmaze Data Center - Beloit — Beloit / Turtle [P]
- Microsoft Data Center - Kenosha — Kenosha [P]
- Microsoft Data Center Expansion Phase 2 - Mount Pleasant — Mount Pleasant [UC]
- Oppidan Edge Data Center - Beaver Dam — Beaver Dam [P]
- PCH / PNK Wisconsin Rapids Data Center — Wisconsin Rapids [P]
- Vantage Data Centers - Port Washington — Port Washington [UC]
- Viridian APECS Data Center Campus - Janesville — Janesville [P]
Wyoming — 7 projects
- Google Project Tembo (formerly Crusoe/Tallgrass AI Data Center) — Cheyenne [UC]
- Meta Data Center (Project Cosmo) — Cheyenne [UC]
- Microsoft Azure Data Centers - Cheyenne — Cheyenne [E]
- Prometheus Hyperscale - Natrona/Converse County Campus — Casper area [P]
- Prometheus Hyperscale - WY-1 (Evanston Campus) — Evanston [P]
- Related Digital Data Center (CoreWeave Campus) — Cheyenne [UC]
- Wind River Reservation Data Center Feasibility Study — Unknown [P]
What the list does—and does not—prove
A public announcement is not the same as a completed project. Data centers can spend years in zoning, utility interconnection, financing and environmental review. Developers may announce a campus at full build-out even when only the first building has financing or power. Some proposals will be delayed, resized, sold or canceled.
The count is also not a measure of current electricity demand. A 1-gigawatt campus can be energized in stages, and the nameplate capacity disclosed for a future campus may be far above the load of its first operating phase. The Energy Information Administration says the fastest near-term load growth is expected in ERCOT and PJM, the grid regions covering Texas and much of the Mid-Atlantic, where this tracker also shows the densest pipelines.
Investment totals require similar caution. The Federal Reserve’s project-level research estimates data center investment could reach a $370 billion annualized pace in the second quarter of 2026, but its 2027 range spans $360 billion to $930 billion depending on how many plans are abandoned and how quickly projects move from planning to construction. That uncertainty is why this tracker keeps project-level figures rather than presenting one seemingly precise national sum.
Why the pipeline matters
Data centers consumed about 4.4% of U.S. electricity in 2023, according to the Department of Energy, and the department’s 2024 national study projected a rise to 6.7% to 12% by 2028. The EIA now expects data centers to be a major driver of U.S. electricity-demand growth and says long lead times for power plants and grid connections limit how quickly supply can catch up.
For communities, the practical questions come before the servers turn on: who pays for substations and transmission, whether water use is disclosed, how tax incentives are structured, what backup generation is permitted, how many permanent jobs are guaranteed and whether a phased campus has enforceable build deadlines. A long project list is useful only if residents, regulators and investors can distinguish a proposal from an approved, financed and energized facility.

What to watch next
The two federal-site selections added after the database snapshot still face negotiations and approvals. Paducah’s power-service agreement requires state regulatory review, while the Savannah River selection must clear lease negotiations, permitting, safety and security evaluations. Elsewhere, utility interconnection queues, local moratoriums, zoning votes and power-supply contracts will determine which of the 684 pipeline entries become operating facilities.
This tracker is dated July 30, 2026. The underlying projects change frequently. Readers who know of a missing project or a status change should consult the source database’s documentation and submission process so the public record can be corrected at the facility level.
Sources and methodology
- Server Country U.S. Data Center Project Database, snapshot dated July 17, 2026; CC BY 4.0.
- Complete project database JSON export, downloaded July 30, 2026.
- FracTracker U.S. Data Centers Tracker methodology, April 7, 2026.
- Associated Press report on the Paducah selection, July 30, 2026.
- NNSA selection of Amentum at Savannah River, July 20, 2026.
- DOE announcement of the PORTS Technology Campus, March 20, 2026.
- DOE national data center electricity-use report summary, Dec. 20, 2024.
- EIA analysis of data-center-driven load growth, March 12, 2026.
- Federal Reserve project-level investment study, updated July 16, 2026.